Hospital Electrical Infrastructure Upgrade and Standby Generation

Colin Bygraves

Colin Bygraves Director of Technical Services

Friday, 13th November 20263 min read

Project summary

  • Client: Confidential healthcare provider
  • Location: Wales
  • Construction value: £180,000

We were appointed to deliver project management, electrical design, technical specification and construction oversight for a hospital electrical infrastructure upgrade, including the installation of a standby generator to improve resilience and continuity of critical services.

Project overview

The project involved the design, procurement support, installation and commissioning of a new electrical supply arrangement and standby generator within a live healthcare environment.

Early-stage activity focused on surveys and technical assessments of the existing electrical infrastructure, alongside coordination of generator siting, cable routes, groundworks and operational constraints.

The works were carefully planned to maintain hospital operations, requiring close coordination with the client’s estates team and strict control over access, shutdowns and commissioning activities.

Scope of services

We supported the client across the full project lifecycle.

Pre-construction

  • Review of existing electrical infrastructure and capacity
  • Coordination of site surveys and buried services checks
  • Planning of generator location, cable routes and groundworks
  • Identification and mitigation of operational risks

Design and specification

  • LV distribution design and standby integration strategy
  • Generator performance specification and resilience criteria
  • Cable sizing, containment, earthing and protection coordination
  • Preparation of drawings, schedules and employer’s requirements
  • Technical support during tender process

Construction phase

  • Programme monitoring and progress reporting
  • Site inspections and quality reviews
  • Contractor design and submittal reviews
  • Management of RFIs and technical queries

Commissioning and handover

  • Review and witnessing of testing and commissioning
  • Verification of load-bank testing and changeover operation
  • Review of as-built drawings and O&M documentation
  • Support through final handover and completion

Delivery approach

The project was procured via a single-stage competitive tender. We remained client-side throughout, providing independent oversight and ensuring quality and compliance during delivery.

The contractor and specialist suppliers developed detailed installation and commissioning information, which we reviewed against the design intent and project requirements.

Key challenges

Live operational environment
All works were planned around hospital activities, with strict controls on access and operational continuity.

Existing infrastructure uncertainty
Multiple surveys were undertaken to confirm buried services and existing electrical systems before works commenced.

Groundworks and generator integration
Early coordination of foundations, trenching and cable routes reduced the risk of redesign during construction.

Resilience requirements
The design prioritised reliability, safe changeover and maintainability to meet operational needs.

Outcomes

The project delivered a resilient standby power system and upgraded electrical infrastructure, providing:

  • Improved reliability of electrical supply
  • Clear and coordinated technical design
  • Controlled and well-managed construction delivery
  • Successful commissioning and operational verification
  • Structured and complete handover documentation

The installation was confirmed to be operating as intended following commissioning and post-completion review.

Performance

  • Delivered within the pre-agreed fee
  • Completed within programme
  • Delivered within the £180,000 construction budget
  • No critical defects at handover

Client feedback

Post-completion review with the client’s estates team confirmed a high level of satisfaction with:

  • Project management and communication
  • Technical oversight and coordination
  • Quality of installation and documentation

Confidentiality note

Client name and specific project identifiers have been withheld due to confidentiality requirements.